ADam Repairs
Town project name: West Fork Eno Reservoir Dam Repairs
- Project estimate in the plan
- $2.9MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- $195,540 in FY2027Plus $23,290 in the current project budget; payment date not supplied.
- Other planned funding
- $149,350 in FEMA reimbursementsCurrent budget and future funding combined; dates in source details.
- Borrowing in the capital plan
- $2,547,660 in FY2027The debt schedule does not supply the matching loan amount, rate or term.
The plan’s summary and detailed cost table differ by $54,520. This estimate follows the summary.
Annual loan payment · principal + interest$329,933Scheduled payment in FY2033
- Payment years shown
- 11 fiscal years
- Payment years
- FY2028–FY2038
- Loan term
- Not supplied
Budget details & sources
Project estimate: $115,840 current project budget + $2,800,000 of planned project outlays = $2,915,840. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
Grants / reimbursements: $92,550 in the current project budget; $56,800 in FY2027.
The summary and funding plan show $2.8M in 2027; the detail expenditure table totals $2,745,480. The $54,520 difference remains unresolved.
CIP borrowing is $2,547,660 FY2027; loan-assumption principal, interest rate and term are not present in the debt workbook. Do not substitute the $2.8M capital funding plan as loan principal.
CIP page 72 cites a preliminary repair estimate of $2M–$3M; extent of repairs depends on further investigation.
Scheduled repayments are $164,967 in FY2028, $329,933 a year in FY2029–FY2037, and $164,967 in FY2038.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 72–73.
Source: Debt Service Projections — Dam Repairs repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D23:Y23
BEno River Interceptors · East
Town project name: Eno River Interceptors Upgrade - East
- Project estimate in the plan
- $6.0MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- No separate fund transfer listedThe funding plan uses the borrowing and other sources shown here.
- Other planned funding
- $2,830,000 in development and facilities feesCurrent budget and future funding combined; dates in source details.
- Planned borrowing
- $3,120,000 in FY2029
The plan’s narrative and funding table describe different borrowing amounts. This card follows the funding table and debt schedule.
Annual loan payment · principal + interest$404,054Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2030–FY2039
- Assumed interest rate
- 5%
Budget details & sources
Project estimate: $750,000 current project budget + $5,200,000 of planned project outlays = $5,950,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
Capital facilities fees: $750,000 in the current project budget.
System development fees: $2,080,000 in FY2027.
The narrative seeks a $5.2M construction loan; the table instead splits $5.2M between fees and debt.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 40–41.
Source: Debt Service Projections — Eno River Interceptors · East repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D31:Y31; 'Projected Assumptions'!C20:H20
CElizabeth Brady Pump Station
Town project name: Elizabeth Brady Pump Station and Force Main Upgrade
- Project estimate in the plan
- $5.3MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- $250,000 in the current project budgetPayment date not supplied; no further fund transfer listed for FY2027–FY2033.
- Other planned funding
- $1,550,000 in development and facilities feesCurrent budget and future funding combined; dates in source details.
- Planned borrowing
- $3,500,000 in FY2029
Annual loan payment · principal + interest$453,266Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2030–FY2039
- Assumed interest rate
- 5%
Budget details & sources
Project estimate: $1,000,000 current project budget + $4,300,000 of planned project outlays = $5,300,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
System development fees: $450,000 in the current project budget; $800,000 in FY2027.
Capital facilities fees: $300,000 in the current project budget.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 38–39.
Source: Debt Service Projections — Elizabeth Brady Pump Station repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D32:Y32; 'Projected Assumptions'!C21:H21
DUS-70A Business Water
Town project name: US-70A Business Water Improvements
- Project estimate in the plan
- $5.7MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- No separate fund transfer listedThe funding plan uses the borrowing and other sources shown here.
- Other planned funding
- $3,938,574 in fees and a grantCurrent budget and future funding combined; dates in source details.
- Planned borrowing
- $1,736,426 in FY2030
Annual loan payment · principal + interest$224,875Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2031–FY2040
- Assumed interest rate
- 5%
Budget details & sources
Project estimate: $305,000 current project budget + $5,370,000 of planned project outlays = $5,675,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
System development fees: $275,000 in the current project budget; $50,000 in FY2029; $2,357,131 in FY2030.
Grants / reimbursements: $30,000 in the current project budget.
Capital facilities fees: $1,226,443 in FY2030.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 62–63.
Source: Debt Service Projections — US-70A Business Water repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D27:Y27; 'Projected Assumptions'!C16:H16
ESewer Equalization Basin
- Project estimate in the plan
- $2.2MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- No separate fund transfer listedThe funding plan uses the borrowing and other sources shown here.
- Planned borrowing
- $2,200,000 in FY2030
Annual loan payment · principal + interest$284,910Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2031–FY2040
- Assumed interest rate
- 5%
Budget details & sources
Project estimate: $0 current project budget + $2,200,000 of planned project outlays = $2,200,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 46–47.
Source: Debt Service Projections — Sewer Equalization Basin repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D28:Y28; 'Projected Assumptions'!C17:H17
FExchange Club Interceptors
- Project estimate in the plan
- $2.9MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- $360,000 in the current project budgetPayment date not supplied; no further fund transfer listed for FY2027–FY2033.
- Other planned funding
- $20,000 in development feesCurrent budget and future funding combined; dates in source details.
- Planned borrowing
- $2,500,000 in FY2030
Annual loan payment · principal + interest$323,761Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2031–FY2040
- Assumed interest rate
- 5%
Budget details & sources
Project estimate: $380,000 current project budget + $2,500,000 of planned project outlays = $2,880,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
System development fees: $20,000 in the current project budget.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 44–45.
Source: Debt Service Projections — Exchange Club Interceptors repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D30:Y30; 'Projected Assumptions'!C19:H19
GHasell Water Tank
Town project name: Hasell Water Tank Replacement
- Project estimate in the plan
- $5.8MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- $395,000 in FY2030Plus $95,000 in the current project budget; payment date not supplied.
- Other planned funding
- $115,000 in prior-project funds, bond proceeds and a grantCurrent budget and future funding combined; dates in source details.
- Planned borrowing
- $5,240,000 in FY2031
The plan’s narrative describes different funding sources. This card follows the funding table and debt schedule.
Annual loan payment · principal + interest$678,604Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2032–FY2041
- Assumed interest rate
- 5%
Budget details & sources
Project estimate: $210,000 current project budget + $5,635,000 of planned project outlays = $5,845,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
Remaining funds from prior project: $43,522 in the current project budget.
Grants / reimbursements: $40,000 in the current project budget.
Remaining bond proceeds from prior project: $31,478 in the current project budget.
The narrative describes leftover funds, development fees and operating transfers; it does not match the future debt shown in the table.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 56–57.
Source: Debt Service Projections — Hasell Water Tank repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D24:Y24; 'Projected Assumptions'!C13:H13
HEno River Interceptors · West
Town project name: Eno River Interceptors Upgrade - West
- Project estimate in the plan
- $2.1MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- $350,000 in FY2030
- Planned borrowing
- $1,790,000 in FY2031
Annual loan payment · principal + interest$194,097Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2032–FY2041
- Assumed interest rate
- 1.5%
Budget details & sources
Project estimate: $0 current project budget + $2,140,000 of planned project outlays = $2,140,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 42–43.
Source: Debt Service Projections — Eno River Interceptors · West repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D25:Y25; 'Projected Assumptions'!C14:H14
ICates Creek
Town project name: Cates Creek Outfall Upgrade
- Project estimate in the plan
- $8.4MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- $517,538 in FY2032; $100,000 in FY2033Plus $195,000 in the current project budget; payment date not supplied.
- Other planned funding
- $3,187,462 in developer contributions and assessmentsCurrent budget and future funding combined; dates in source details.
- Planned borrowing
- $4,400,000 in FY2032
The plan’s narrative and tables differ on timing. This card follows the tables.
Annual loan payment · principal + interest$569,820Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2033–FY2042
- Assumed interest rate
- 5%
Budget details & sources
Project estimate: $195,000 current project budget + $8,205,000 of planned project outlays = $8,400,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
Developer contribution: $1,708,498 in FY2027.
Special assessment revenue: $996,502 in FY2027; $225,000 in FY2031; $257,462 in FY2032.
These are planned funding sources, not verified receipts or executed commitments. The narrative timeline differs from the expenditure table; the table controls the displayed schedule.
Narrative page 36 lists a different sequence and amounts; use the page 37 expenditure/funding table for this display. Do not total narrative and table together.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 36–37.
Source: Debt Service Projections — Cates Creek repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D26:Y26; 'Projected Assumptions'!C15:H15
JBellevue Mill
Town project name: Bellevue Mill Interceptor Upgrade
- Project estimate in the plan
- $1.5MCurrent budget + planned project outlays through FY2033
- Water & Sewer cash contributions
- $140,000 in FY2030; $40,000 in FY2031
- Planned borrowing
- $1,320,000 in FY2032
Annual loan payment · principal + interest$170,946Scheduled payment in FY2033
- Repayment term
- 10 years
- Payment years
- FY2033–FY2042
- Assumed interest rate
- 5%
Budget details & sources
Project estimate: $0 current project budget + $1,500,000 of planned project outlays = $1,500,000. Current budget does not mean money already spent. This is the cost covered by this plan, not a complete lifetime cost.
Source: FY2027–FY2033 Capital Improvements Plan, PDF pp. 34–35.
Source: Debt Service Projections — Bellevue Mill repayment schedule.
Workbook: Debt Service Projections.xlsx
Cell references: Debt!D29:Y29; 'Projected Assumptions'!C18:H18